Meeting Minutes:
TRCC testing infra done, asked devs to work on tests
TRCC aims to get project done by mid march
TRCC sprint outline
Inga started phase 2 of the project —> frontend focus
Devs working on frontend right now
no longer pairing seniors with juniors
gave them a bunch of tickets to choose from + deadline
designers working on the reports page (most intensive page)
Phase 3 —> polish login entry and journal entry pages
Phase 4 —> Implementation of the reports
Goal to be done by mid march
MADE has completed authentication + volunteer sign up
need to create an import system
need to remind devs to include tests
Sophia has not informed if she’s met with Anders
Designs from designers seem to work well for client
Goal to finish dev by march, want to leave 2-3 weeks for testing